Project Charter Document: Office Relocation Project

 

1.1 Charter Element

The project of office relocation would be based on the consideration of the effective factors for integrating the development of innovative information management. The project deals with relocation of the office. The lease of old office has been expired. In this scenario, management of the organisation has decided to relocate the office. In the project, systems and other documents will be shifted with having aim to damage the products and working hour as minimum as possible.  Hence, the project aims to develop the following aspect that will be helpful to complete the project successfully. The charter elements list the factors for ensuring the development of the factors for improving the development of innovative information management. The following are the elements of innovative information management. In the project, office relocation it is essential to select the best possible method for completion of the project.

 

 

Charter Element Answers
Background Why?
Business Case Why?
Lesson Learned How?
Milestone Schedule When?
Resources How Much?
Risks, Assumptions, and Constraints Whoa!
Scope What?
Signatures and Commitment Who?
Stakeholders Who?
Success Criteria What?
Team Operating principles How?

 

1.2 Charter Decision Matrix

The charter decision matrix would be helpful for aligning the continuous. The charter document would be helpful for the organisation to select the best possible methods for the organisation. On the other hand, approval, communication and education, metrics and potential risk factor selection can be helpful for the project to identify the risks and complete the project successfully.

 

Project Name: Office Relocation
Date: 28-05-2019
Approvals Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Communication and Education Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Complexity Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Metrics Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Multidisciplinary Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Potential Risk Factor Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Resources Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Staff Commitment Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Technology Involvement Few would be required for successful completion of project Average would be required for successful completion of project Most of the would be required for successful completion of project
Validating the maximum number of checks in this area 2/9 5/9 2/9
No Charter Needed Mini Charter is needed Detailed Charter is needed

 

1.3 Project Selection Matrix

The following is the project selection matrix; the project selection matrix is helpful to understand the process of the project.

 

Project/Selection Criteria Criteria A Criteria B
Weight: 5 10 Total
Landscaping project 7 5
(5*7=) 35 (5*10=) 50 (35+50=) 85
Project/Selection Criteria Potential Monetary Gain Success Probability Social Opinion
Weight: 5 10 3 Total
Construction Project has been selected as: International Hotel, Hawaii 10 5 5
Construction Project has been selected as: Local Hotel, Brisbane 8 6 4
Infrastructure Project has been selected as High Speed Rail – Sydney to Melbourne 9 3 8
Investment project: It has been selected as The Old Farm House 7 7 10
Construction Project: International Hotel, Hawaii

 

1.4 Project Description

The project as office relocation would involve the development of the improved work performances management. The project of office relocation would be based on the consideration of the effective factors for integrating the development of innovative process of information management. The charter elements list specific factors for ensuring the development of the factors for improving the development of information management.

 

1.5 Project Scope Statement

The project of office relocation would involve the development of the improved work performances management. The project of office relocation would be based on the consideration of the effective factors for integrating the development of innovative information management. The project scope statement would include the,

  • Development of documentation for project work alignment.
  • Alignment would also involve the contiguous management of the project works
  • Information management would be developed with the continuous

 

 

1.6 Scope Overview

The project of office relocation would be dependent on Development of documentation for project work alignment, alignment would also involve the contiguous management of the project works, and Information management would be developed with the continuous innovation and technology.

 

1.7 Milestone Schedule and Deliverables

The milestone schedule and the deliverables for the office relocation project are given below,

 

WBS Task Name Duration Start Finish
0 Office Relocation Project 6 wks Wed 01-05-19 Tue 11-06-19
1    First Phase 1 wk Wed 01-05-19 Tue 07-05-19
1.1   Collecting Information 2 days Wed 01-05-19 Thu 02-05-19
1.2   Development of work requirements 1 day Fri 03-05-19 Fri 03-05-19
1.3   Selection of relocation date 1 day Mon 06-05-19 Mon 06-05-19
1.4   Contract Hiring 1 day Tue 07-05-19 Tue 07-05-19
1.5   D1: Date of relocation 0 days Tue 07-05-19 Tue 07-05-19
1.6   M1: Milestone date 0 days Tue 07-05-19 Tue 07-05-19
2    Second Phase 1.6 wks Wed 08-05-19 Fri 17-05-19
2.1   Relocation activities are developed 2 days Wed 08-05-19 Thu 09-05-19
2.2   Development of Schedule 3 days Fri 10-05-19 Tue 14-05-19
2.3   Project Plan is developed 1 day Wed 15-05-19 Wed 15-05-19
2.4   Management plan is made 2 days Thu 16-05-19 Fri 17-05-19
2.5   D2: Project Plan 0 days Fri 17-05-19 Fri 17-05-19
2.6   M2: Project Plan Approval 0 days Fri 17-05-19 Fri 17-05-19
3    Third Phase 1.4 wks Mon 20-05-19 Tue 28-05-19
3.1   Technology Development 1 day Mon 20-05-19 Mon 20-05-19
3.2   Dismantling of structure 1 day Tue 21-05-19 Tue 21-05-19
3.3   Facilities are removed 2 days Wed 22-05-19 Thu 23-05-19
3.4 Movable Objects are packed 1 day Fri 24-05-19 Fri 24-05-19
3.5   Disposal of the immovable 1 day Mon 27-05-19 Mon 27-05-19
3.6   Paying of bills 1 day Tue 28-05-19 Tue 28-05-19
3.7   D3: Vacated Office 0 days Tue 28-05-19 Tue 28-05-19
3.8   M3: Shifting of office 0 days Tue 28-05-19 Tue 28-05-19
4    Fourth Phase 1.2 wks Wed 29-05-19 Wed 05-06-19
4.1   Arrived at new location 1 day Wed 29-05-19 Wed 29-05-19
4.2   Things are received 1 day Thu 30-05-19 Thu 30-05-19
4.3   Development of infrastructure 2 days Fri 31-05-19 Mon 03-06-19
4.4   Furniture and Fixtures are added 1 day Tue 04-06-19 Tue 04-06-19
4.5   Installation of furniture and fixtures’ 1 day Wed 05-06-19 Wed 05-06-19
4.6   D4: New office facility 0 days Wed 05-06-19 Wed 05-06-19
4.7   M4: Shifting to new office 0 days Wed 05-06-19 Wed 05-06-19
5    Fifth Phase 0.8 wks Thu 06-06-19 Tue 11-06-19
5.1   Documentation of final reports 2 days Thu 06-06-19 Fri 07-06-19
5.2   Documents are submitted 1 day Mon 10-06-19 Mon 10-06-19
5.3   Review and Sign off 1 day Tue 11-06-19 Tue 11-06-19
5.4   D5: Final Documents 0 days Tue 11-06-19 Tue 11-06-19
5.5   M5: Project End 0 days Tue 11-06-19 Tue 11-06-19

 

1.8 Initial Risk Identification

 

Project (Potential) Risks Risk Owner Contingency Plans
Delay in completion Planner Time Management Plan
Human Mistakes HR manager Training and Development
Lack of Information Project Owner Authentic information sources must be addressed
Over Budget Project Owner Contingency Budget

 

1.9 Resources Required

 

Resource Name Type Standard Rate
Project Manager Work $98.00/hr
CIT Manager Work $88.00/hr
Admin Manager Work $78.00/hr
Contractor Work $83.00/hr
Workers Work $68.00/hr

 

Planner Work $73.00/hr
Removal Cost Material $18,000.00
Development Cost Material $32,000.00
Outstanding Bill Material $8,546.00
Installation Bills Material $15,350.00

 

1.10 Gantt chart

 

 

1.11 WBS

 

 

1.12 Initial Stakeholder Identification

 

Stakeholder Interest in Project Priority(High/Medium/Low)
Client The customer is useful for keeping up the quality and giving the fundamental quality components to the task High
End users The finishing of the venture and the utilization of the last work arrangement for facilitating the improved work advancement Low
Investors Picking up from the arrangement of the ventures and the development of the inventive arrangement of the offices Medium
Project Manager Finishing of the venture would empower the administration of the exercises advancement Low

 

1.13 Team Operating Principles

 

# Team operating principle
1 It is vital for separating the works dependent on the combination of the aptitudes and capabilities of the simple work arrangement improvement.
2 It turned out to be evident that the correspondence the board would be useful for guaranteeing the consummation of the works with the utilization of the creative data
3 The task timetable would be created with the continuation of the inventive data the board for the thought of the viable arrangement of works

 

1.14 Lessons Learnt

 

# Lesson
1 I have had the capacity to comprehend the utilization of the venture the board devices and procedures for adjusting the advancement of the inventive data the executives
2 I have been able to use the risk management processes for enabling the continuation of the innovative information alignment for mitigating the risk factors
3 It turned out to be simple for building up the undertaking contract records with the proceeded with the board for suggesting works.

 

1.15 Commitment

 

Sponsor Department / Organization Signature
Heath Kim Lee CEO Heath Kim Lee
Project Manager Department / Organization Signature
<<name of the student>> Branch Manager <<name of the student>>
Core Team Members Department/ Organization Signature
Jonathan Jones Sales Department Jonathan Jones
Laurance Keith Sales Department Laurance Keith
Amanda Lee Sales Department Amanda Lee

 

Bibliography

Al-Harithy, M. M. (2016, November). Barriers of knowledge acquisition in telecommunications companies in Saudi Arabia: An exploratory study on Etihad EtisalatMobily. In Communication, Management and Information Technology: International Conference on Communciation, Management and Information Technology (ICCMIT 2016, Cosenza, Italy, 26-29 April 2016) (p. 313). CRC Press.

 

AlMazrouei, H., &Pech, R. J. (2015).Working in the UAE: expatriate management experiences. Journal of Islamic Accounting and Business Research, 6(1), 73-93. http://www.ijbts-journal.com/images/column_1451930351/3%20Hanan%20Al%20Mazrouei.pdf

 

Awad, A. (2018). The Effect of Human Resources Competencies on a Firm Performance: A Marketing Perspective (With Reference to Firms Located in UAE). Asian Business Research, 3(1), 60.http://journal.julypress.com/index.php/abr/article/viewFile/350/270

 

Coban, A., Yigit, F., Kalkavan, H., Kizil, C., &Seker, S. E. (2016).Macroeconomic facts for Telecom Industry in MINT Countries. Procedia Economics and Finance, 39, 156-164.

 

https://www.sciencedirect.com/science/article/pii/S2212567116302672/pdf?md5=874cbfdb2b77bb6dd4e98c1f9bfb71eb&isDTMRedir=Y&pid=1-s2.0-S2212567116302672-main.pdf&_valck=1

 

Heagney, J. (2016). Fundamentals of project management. Amacom.

Kendrick, T. (2004). The project management toolkit: 100 tips and techniques for getting job right. Project Management Institute, AMACOM Div American Mgmt Assn, 233.

 

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

 

Kloppenborg, TJ, Anantatmula, V & Wells, KN 2018, Contemporary Project Management, 4 edn, Cengage Learning, Boston, MA, USA.

 

Lasserre, P. (2017). Global strategic management.Macmillan International Higher Education.

https://gsom.spbu.ru/files/upload/master_program/materials/international_business_strategy/lasserre_globalisation_indices.pdf

 

Laws, R., & Mo, N. (2015).Product &Pricing Standardization within the Global Mobile Network Operator Industry.http://www.diva-portal.org/smash/get/diva2:839694/FULLTEXT01.pdf

 

Reich, B. H., & Wee, S. Y. (2006). Searching for Knowledge in the PMBOK® Guide. Project Management Journal, 37(2), 11-26.

 

Zwikael, O. (2009). The relative importance of the PMBOK® Guide’s nine Knowledge Areas during project planning. Project Management Journal, 40(4), 94-103.